The focus this past week continued to be on connecting homes to the new sanitary sewer and connecting new water services. Additionally, storm sewer was installed on Merrill Ave. and Sanford St. from Merrill Ave. to Hamilton Ave. The focus this week will be on continued connections to the home for water and sanitary sewer.

 

Work Completed Last Week

  • Contractor continued connecting homes to the new sanitary sewer mainline.
  • Contractor continued work on water service replacement.
  • Contactor placed sanitary sewer from Strong Ave. towards the South.
  • Contractor placed storm sewer on Merrill Ave. and on Sanford St. from Merrill Ave. to Hamilton Ave.

 

Anticipated Work This Week

  • Watermain tie-in at Apple Ave. scheduled for Tuesday, 05/09/2023.
  • Continuation of connecting homes to the new sanitary mainline.
  • Continuation of connecting new water services.
  • Continuation of connecting new water services to meters inside of homes.
  • Sanitary sewer extension on Merrill Ave, West of Sanford.
  • Completion of Storm Sewer on Sanford St.
  • Closure of Jefferson St. on Tuesday 05/09/2023 for water service main tap with an anticipated reopening by the end of the day.
  • Begin building road on Sanford St. from Strong Ave. toward the North.