Week 5 on Southern Avenue is complete! The base course of asphalt was installed this morning. Here are some details:

 

Work Completed Last Week

  • Concrete curb and gutter was installed throughout the project on Southern Ave.
  • Aggregate base was installed over the prepared sand throughout the project area and fine graded in preparation for asphalt
  • A rain garden was installed on Peck Street in front of the Child Abuse Council of Muskegon County building (1781 Peck St).

 

Anticipated Work This Week

  • The first layer of asphalt is being installed today (Monday, November 1).
  • Concrete sidewalk, driveways and ADA ramps will be installed this week.
  • Manhole castings will be raised up to final grade this week.
  • Top soil will begin to be installed over disturbed grassy areas on Southern Ave.
  • Final paving may be completed as soon as the end of the week.