Progress Report:

Water main installation at the Ox Creek stream crossing has been completed. Water service installation to property lines has begun on S Euclid between Britain Ave and Highland Ave. All intersections and driveways that were disturbed due to water main construction have been restored.

Upcoming Work:

Pressure testing and disinfection of the water main on S Euclid Ave between Empire Ave and Britain Ave will occur over the next couple of weeks. Water service installation to property lines will also continue over the next week.