Pipestone Road
After a short delay, Pipestone Road has been restored and will be open to traffic by the end of the day!
Directional Drill Near the Hampton Inn
Force main installation by horizontal directional drill underneath the unnamed road near the Hampton Inn is complete. With this completed, approximately 95% of all the force main on the project has been installed.
Gravity Sewer Construction Near the Hampton Inn
Gravity sewer installation between the new lift station site and Hampton Inn is near completion. Once this run of sewer has been completed, construction of 21” gravity sewer in the area between the Hampton Inn and I94 will continue.