Carpenter crews are working on the kayak/fishing platform, as well as the steps between the lake and the City Park property along Lake Ridge Drive this week. In addition, aggregate should be placed as base for the brick paver blocks at the rest area near NMC.

Elmer’s needed to repair the pile hammer, but it should be up and running this week, and they will continue to proof piles in place for the Boardman Lake Boardwalk.

It is possible that crews will begin clearing for construction of the bridge abutments for the bridges from Logan’s Landing to Medalie Park, and the Medalie Park to the existing trail on the east side of Boardman Lake. Sheet piling for these abutments should arrive in the next few weeks.

 

Next Week

Work will continue on these same tasks. We anticipate that they will be working on the piles for another month.