Progress Report

My-Con has completed installed pipe to the west of 144th Avenue, along with the directional drill under 144th Avenue. Force main installation to the east end of the Hortech Property should be completed this week with installation of cleanouts and air release structures. Crews are working on restoration along these areas.

My-Con and Dewitt Trenching have moved to the pump station area at Birchview Drive (Hathaway Lakes) and are beginning the direction drill across the wetland area to the west of Birchview. Please be cautious of construction equipment in this residential area and avoid the immediate construction area. The North Bank Trail remains closed from Birchview to 148th Avenue. Crews will be working on restoration, cleanouts, air release structures, and the directional with the remaining open cut force main to be completed following drill operations.