All underground utility improvements on Southern Avenue are scheduled to be completed by Tuesday, October 19.  Kamminga & Roodvoets has already begun to put the roadway back together. Here are the details:

 

Work Completed This Week

  • The sanitary sewer at Jefferson Avenue was completed and wastewater flow has now been diverted to Peck Street instead of through the High School property.
  • The mainline storm sewer was installed Sanford Street to Jefferson Street.
  • Five lead/galvanized water services were replaced with copper piping.

 

Anticipated Work Next Week

  • The remainder of the storm sewer catch basin leads will be installed by tomorrow (Tuesday).
  • Aggregate base will be installed on Southern Avenue before the end of the week.
  • Concrete curb and gutter will begin to be installed by Kamminga & Roodvoets on Friday and Saturday this week.