Work Completed this Past Week

  • All concrete curb, sidewalk and concrete driveways have been completed
  • All restoration north of Benston has been completed
  • Work on grading the gravel road base material has started in preparation for asphalt
  • Gravel base material has been placed in all driveways scheduled for asphalt

 

Work Anticipated Week of October 2, 2023

  • Driveway access will reopen for everyone on Monday morning
  • North of Benston, Mears pavement surface will be milled on Monday, October 2
  • Finish grading and compacting the road base gravel south of Benston for possible first layer of asphalt late in the week

 

Work Anticipated Week of October 9, 2023

  • Raise manhole covers and valve lids to final elevations and prepare jobsite for final paving
  • Final restoration of areas south of Benston

 

Week of October 16, 2023

  • Final paving is looking like the middle of the week of October 16 – WEATHER DEPENDENT!
  • Pavement Markings
  • Signage
  • Reopen Road, remove traffic barricades – Job Complete!