Work Completed this Past Week
- All concrete curb, sidewalk and concrete driveways have been completed
- All restoration north of Benston has been completed
- Work on grading the gravel road base material has started in preparation for asphalt
- Gravel base material has been placed in all driveways scheduled for asphalt
Work Anticipated Week of October 2, 2023
- Driveway access will reopen for everyone on Monday morning
- North of Benston, Mears pavement surface will be milled on Monday, October 2
- Finish grading and compacting the road base gravel south of Benston for possible first layer of asphalt late in the week
Work Anticipated Week of October 9, 2023
- Raise manhole covers and valve lids to final elevations and prepare jobsite for final paving
- Final restoration of areas south of Benston
Week of October 16, 2023
- Final paving is looking like the middle of the week of October 16 – WEATHER DEPENDENT!
- Pavement Markings
- Signage
- Reopen Road, remove traffic barricades – Job Complete!