Note: Whitehall road closure scheduled for October 4th. See below map for details.

 

Work completed/in progress:

  • Approximately 350′ of force main installed within Colby Street. Force main installed to just east of ACE Hardware drive.
  • Connection valving installed at Whitehall Road.

 

Anticipated work activities for the coming week:

  • Continue pipe installation within Colby Street and cross Whitehall Road.