Work Completed this Week (October 19–24)

  • 99% of removals were completed
  • Temporary gravel walks were installed along Ludington Avenue, and adjacent the building to maintain access to businesses.

 

Anticipated Work Next Week (October 26–30)

  • Water main tie in is expected to occur on Tuesday, October 27, along with water main installation on Tuesday and Wednesday.
  • The contractor is grading the plaza to establish rough grades and balance the site.
  • Footings for the restroom building are expected to be prepped.

 

Important Items of Note

  • Early in the week of November 2 the restroom building footings will be installed and the contractor is planning to make progress on the installation of light pole bases, shelter pilings, and beginning storm pipe installation.