The contractor plans on paving top course of Lake Street from the BL to Olmstead tomorrow, Tuesday 10/31 and Wednesday 11/1.

This section of Lake Street will remain open to traffic and accessible to all roads including Lamont/Healy.

Contractor will have people stationed at the intersections directing traffic during paving operations. The plan is to start at the West end (BL) at around 7:30 am Tuesday morning, paving the South lane first.

Please reach out if anyone has any issues with access. Zac Culbert will be onsite during all paving operations and can be reached by phone or email.