It was an exciting week on Mears Avenue in Whitehall this week as we saw some serious progress towards completion!  Here is a quick update on the construction progress on Mears Avenue in Whitehall recently and what to expect coming up:

 

Work Completed this Past Week

  • Contractors graded the gravel and prepared it for asphalt
  • Roadway was milled north of Benston and manholes were adjusted for the new pavement north of Benston
  • Base course of asphalt was placed south of Benston to the curve south of Pinecrest

 

Work Anticipated Week of October 9, 2023

  • Manhole structures will be raised south of Benston to final layer of asphalt elevation
  • Paving of top course of asphalt for the entire project from Gibbs south to the curve south of Pinecrest will be done all at once – this could happen late in the week, or possibly early the week of October 16
  • Signs will be replaced along the route

 

Work Anticipated Week of October 16, 2023

  • If top course of paving wasn’t completed, it will be done this week
  • Pavement markings will be completed
  • Signage and restoration will be completed
  • Reopen Road, remove traffic barricades – Job Complete!