Last week, work on Airway Street was pretty much wrapped up with hydroseeding completed. The remaining work on Airway is at the KIA Dealership as the contractor is waiting for the sprinkler system to be relocated out of the right of way. As soon as this is complete, Al’s Excavting can return and finish up this section as well.
On Jericho Avenue, Al’s Excavating continues to work hard on the final retaining wall and placing the gravel base from Kroes Street to Peter Creek Drive. They hope to be ready to pave this section by the end of the week. In addition, next week crews will move to the north side of the project where they will start work on the storm sewer north of the Rogue River.