The focus this week continued to be on placing sanitary sewer main for Phase I on Griswold Street. The focus next week will be on finishing the sanitary sewer outlined in Phase 1, as well as curb infill and road rebuild.
Work Completed Last Week
- The Contractor continued placing sanitary sewer main on Griswold Street for Phase 1.
- The Contractor placed aggregate base in preparation for asphalt up to the Ocean County Services building.
Anticipated Work This Week
- The Contractor will finish placing sanitary sewer mainline and sanitary sewer manholes outlined for Phase I.
- The Contractor will begin concrete curb infill and road rebuild on Griswold Street for Phase 1.