Progress Report:
- Underground Completion: We are pleased to report that all underground utility work on the project is now complete! This is a major milestone allowing everyone to focus remaining efforts on completion of the streets, sidewalk, driveways, and other surface work.
- Lincoln Street: The focus next week will continue to be on concrete work. Curb and gutter that was constructed out of compliance with project specifications is being removed. We are anticipating several days of concrete pouring with significant progress toward completion of remaining concrete work next week.
- Maple, Fremont, and Courtland Streets: Various work with manhole covers, sidewalks, and miscellaneous items remain to be completed. We are eager to see remaining miscellaneous items completed in anticipation of top course pavement in the street and project completion.