This Week:

  • Dean’s Excavating began water main construction along Summit Avenue at 11 Mile Road.
  • The water main was installed across Summit Avenue, just north of 11 Mile Road, and water main construction continued north along the west side of the road.
  • Summit Avenue is closed to thru traffic, open to local traffic only, and will remain closed throughout October. The posted detour route is Wolven Avenue to the west.

 

Next Week:

  • Dean’s will continue installing water main to the north along the west side of Summit Avenue.
  • There may be periods of the day where your driveway is temporarily impacted by water main construction. Dean’s will work with you to avoid any conflicts with access and restore your driveway with gravel as soon as possible.