This week all work was focused on Phase III with primary work on storm sewer. All water main and sanitary sewer is now complete! Note that a single lane road closure will be implemented on West bound Laketon Avenue starting September 12 which will be in place for the remainder of the project.

 

Work Completed This Week

  • Completed sanitary sewer sewers on phase III.
  • Worked on storm sewer on phase III, storm is 90% complete.
  • Completed all remaining water services.

 

Anticipated Work Next Week

  • Complete storm sewer on phase III.
  • Start grading road and sidewalk for phase III.