Progress Report:

Last week crews from Riverworks Construction worked quickly to finish the framing and decking on the tall boardwalk by 62nd Street. There is still some remaining work to be done on the boardwalks, Such as; installing the railing fencing and final finishing touches, but they are getting close to completing the boardwalks. Kalin Construction also began working on the large block retaining wall that will be constructed along the west end of the tall boardwalk. They will continue working on the retaining wall this week.

Upcoming Work:

As we noted earlier in the project, things will move quickly. Once Kalin Construction finishes the installation of the retaining wall, they will finalize the grading of the aggregate in preparation for asphalt. We are still on track to have the pathway complete by the beginning of October.