Last week, all remaining storm sewer was installed for the project. Grading of the sand grade and installation of aggregate base began in preparation of concrete sidewalk and curb installation. This project is winding down quickly with the end in site. Underground work is essentially complete with only a few loose ends remaining.

 

Work Completed This Week

  • Completed storm sewer on phase III, this completes the storm sewer for the full job.
  • Completed sanitary sewer abandonment on phase III.
  • Completed road striping on phase II.

 

Anticipated Work Next Week

  • Begin concrete walk and curb & gutter placement on phase III.
  • Continue building road on phase III.