Progress Report

148th Avenue was repaved last week and is now reopened to through traffic. This week, My-Con will be working on restoration of the pathway and surrounding landscaping between 148th Avenue and 144th Avenue. DeWitt Trenching will be mobilizing to the pathway this week, setting up their drill rigs in various places along the path, and clearing brush. Due to the amount of construction vehicles expected to be traveling the pathway this week, the entire North Bank Trail will be closed to pedestrian traffic.