Last week on Jericho Avenue, crews from Al’s Excavating continued to prepare the southern section of the pathway for paving while the utility companies worked to relocate their utility conflicts. The crews installed over 1000 feet of subgrade and aggregate base along this stretch, as well as starting the driveway removals and preparing them for the path to come through.
This week, crews will finish the concrete and HMA driveway removals and begin installing the storm sewer on the north end of the project.