Progress Update

Approximately 1,300 feet of sanitary sewer has been installed on Pipestone Road, Carlton Ave, and M139. 80% of the sewer replacement on the project has been completed. The concrete curb and pavement on M139 has been restored.

 

Up Next

Sanitary sewer replacement on Pipestone Rd will continue. Mainline sewer is anticipated to be finished on Wednesday, at which time the Contractor will start working on finishing installing laterals to property lines. Carlton Ave is scheduled to be paved on Wednesday.