Work Completed this Past Week and Recently:

  • All water main work is complete on Seng, Kunz and Aue
  • All water services are installed on Seng, Kunz and Aue
  • Restoration is underway on Seng, Kunz and Aue with backfilling of yards, topsoil and road
  • Water main has been installed on Petrie west of Grand Haven Road
  • Water main between Petrie and Wilson was prepped and pulled into place

 

Work Anticipated Week of September 25, 2023

  • Hydrant installations on Petrie
  • Water main installation on Wilson west of Grand Haven Road
  • Concrete work for curb and gutter at intersections for Seng, Kunz and Aue/Miller on Monday, September 25, 2023 as well as concrete driveway approaches
  • Asphalt repairs on Seng, Kunz and possibly Aue/Miller intersection later next week
  • Some water service connections are possible.

 

Work Anticipated Week of October 2, 2023

  • Finish water main installation on Wilson west of Grand Haven Road
  • Begin testing water main on Wilson and Petrie for final connections to Grand Haven Road water main
  • Lawn restorations on Aue, Kunz and Seng
  • Water service connections may continue

 

Construction is scheduled to be completed in November 2023. Please watch for more information about connecting to the new water main for those residents connecting to the new water main.