Progress Report

This week, My-Con will be finishing grading and topsoiling the stretch of the trail between 148th Avenue and 144th Avenue. DeWitt Trenching will be directionally drilling force main using their drill rig on the east side of 144th Avenue. Both 148th and 144th will be passable to traffic, but drivers are to be cautious near the 144th Avenue trailhead due to the large amount of equipment being temporarily stored at the trailhead parking lot. While My-Con finishes up restoration efforts on the western portion of the project, and crews clear and grub some trees and brush between 144th Avenue and Birchview Drive, the trail will still be closed to pedestrian traffic this week. My-Con hopes to have the portion of the trail between 148th and 144th reopened late next week.