Construction Updates

Important Information

Progress Report:

Riverworks is still continuing efforts constructing the large boardwalk on the corner of Pettis where they are nearly 50% complete with the structural elements of the boardwalk. On the West side of that boardwalk, piles for the smaller boardwalk have been completely installed, but further progress will be slowed until after the larger boardwalk is completed.

Terracon has begun partial removals of driveways along Cannonsburg. Integrity made it on site this week to begin the block wall construction and has made significant progress on the first wall, installing both over 100 feet of base and middle blocks.

Upcoming Work:

Riverworks will continue construction on the larger boardwalk into next week. Terracon will continue removing driveway approaches into next week. Integrity will continue construction on the retaining wall into next week.

Sanitary Sewer main installation has begun on Lexington Avenue and Hadden Street. Sanitary sewer installation will be completed next week on Hadden Street, with water main installation beginning in Hadden toward the end of the week.

Work Completed This Week:

  • Sanitary sewer main installed on Lexington Avenue from Westwood Street to Wickham Drive.
  • Sanitary sewer main installation began on Hadden Street, south of Lexington Avenue.

Anticipated Work Next Week:

  • Complete sanitary sewer main on Hadden Street, north and south of Lexington Avenue.
  • Begin installation of water main on Hadden Street.

Progress Report:

Brenner excavating has almost completely graded and graveled the bike path on Kies, where focused efforts have been on installing storm structures throughout the path and retaining block walls this week. One retaining wall has been complete near Oakview Ridge and the other wall is currently being constructed a couple of properties East. Riverworks has completed pile driving for the boardwalk and is now focusing efforts on installation of structural support

Upcoming Work:

Brenner plans on continuing to install retaining walls into the upcoming week. Riverworks will continue boardwalk construction into next week. As an additional note, paving on Hickory Drive and Luton Park is set to begin on Monday at 8:00 AM.

Progress Report:

The installed water main has passed testing. The contractor will be on site next week to make the final connections early in the week. Following that, the contractor will rebuild the road and prepare for paving the last stretch of 48th Avenue outside of the roundabout.

The roundabout at the intersection of 48th Avenue and Baldwin Street is expected to open around the middle of October.

Notes:

48th Avenue remains closed to through traffic from Port Sheldon Street to Baldwin Street. The intersection at Baldwin Street and 48th Avenue remains closed from every direction for the roundabout construction. Through traffic should continue to follow the posted detour signage.

Residents along 48th Avenue should be aware that crews will be on site restoring the roads and greenspace around the roads.

Local traffic needing access to Sutherland Springs Condominium should do so by turning onto 48th Avenue from Port Sheldon Street.

Progress Report

  • Oakwood Avenue: Structure adjustments have been made, and the road is prepared for final paving.
  • Amsterdam Avenue: Road gravel has been installed and is being shaped and prepared for concrete curb and gutter to be installed.
  • Getty Tank: All work has been completed.
  • Norton: Traffic control signs were posted and notices sent to residents who will have service line replacements
  • Lead Service Lines: Additional services are being replaced in the City near Waalkes, south of Broadway.

Upcoming Work Planned for the Next Few Weeks:

  • Oakwood: Final paving and restoration next week
  • Amsterdam: Concrete curb and gutter, sidewalks, ramps, and shaping the gravel road base for paving
  • Reynolds: Final paving and restoration next week
  • Norton: Between Park and Jefferson Streets, water service replacements, and a new water main in Seminole, south of Norton. The team will install new water main connections and valves at several intersections on Norton Avenue. This will be the last major project this year.

 

Some photos of work this week:

Amsterdam and Fifth Street, looking east

 

Fifth Street, looking north from Amsterdam

 

Water service replacement beginning on Norton, west of 5th Street

Please visit our dashboard for lead service line replacement to see the work that is left to be done:

https://preinnewhof.maps.arcgis.com/apps/dashboards/70a9f6d2e830499fa56eaa58c483f88e#

October is here and our schedule has slipped a bit due to scheduling and weather.  Here is a brief update on the Adrian Tunnel project:

Progress Report

  • Additional sheeting has been installed on the east side prior to additional excavation for wall construction
  • Additional grading and restoration efforts took place to get the site cleaned up on the west side

Upcoming Work Planned for the Next 4-6 Weeks:

  • Excavation for wall footings
  • Installation of east wall footings
  • Installation of the last 2 sections of tunnel
  • Construction of the east poured-in-place concrete walls
  • Backfilling and M-52 Road Restoration
  • Completion of the modular block walls on the west side, including fencing
  • Installation of modular block walls on the east side
  • Masonry on the west parapet wall and around the west tunnel face

Recent construction photo from the site:

Additional steel sheets being installed to protect the banks and make the work safer

 

New sheets prior to wall construction on the east side of M-52

 

Progress Report:

Northland Drive was opened ahead of schedule this week. Dean’s Excavating has been doing some sewer testing this week under the shoulder closure.

Next week, the lane shift along Belding Road will be put back in place on Monday morning. Dean’s will continue sanitary sewer replacement up to Myers Lake. Myers Lake will be closed to thru traffic end of next week or beginning of the following week to allow the sanitary sewer to be replaced through the intersection. Myers Lake traffic will be detoured and the closure is expected to last for around 1 week.

Sanitary sewer construction is scheduled to wrap up by middle of October with project restoration scheduled to be completed by the end of October.

Kentwood Excavating has their subcontractors scheduled to complete final asphalt and concrete work today (10/2). Once this is completed, Kentwood can complete the final topsoil work, irrigation system repairs, and hydroseed the disturbed areas. Kentwood’s crew will also be working on addressing punch list items throughout the project area over the course of the next few weeks.

Progress Report:

Kalin Construction and their subcontractors were able to complete Phase 2 (Northland Drive full closure) well ahead of schedule and traffic has been restored. Phase 2 included excavating a 60-foot-wide trench, installing four storm sewer runs, two electrical conduits and the pedestrian tunnel across Northland Drive.

Upcoming Work:

Work will continue on the approaches on both sides of Northland Drive throughout the rest of the construction season. The only ongoing traffic restriction will be the right turn lane at 7 Mile Road for northbound traffic.

Progress Report:

Cutting Edge and S&S Sprinkling are continuing their work on completing restoration and sprinkling repairs throughout the neighborhood.

Cutting Edge hopes to be completed with restoration by October 15.