Construction Updates

Important Information

K&R completed tree clearing. No additional project work on Contract No. 2 anticipated until spring.

Milbocker remains off-site awaiting arrival of additional force main materials. Milbocker is planning to re-mobilize the week of December 2.

Work completed/in progress:

  • The first wall pour was completed this week (see photos).
  • Conduit and rebar are installed for the second wall pour.

Anticipated work activities for the coming week:

  • Forms will be stripped and moved to the next wall section. The second wall pour is scheduled for next week Wednesday.

Work completed/in progress:

  • Completed tree clearing activities and silt fence installation on MCRRC property and Ensley Road.
  • Force main materials continue arriving on-site.

Anticipated work activities for the coming week:

  • Complete tree clearing activities on Price Road and Sherman Boulevard.
  • Continue receiving additional force main materials.
  • Complete butt-fusion training and initial acceptance testing.
  • Install dewatering system on MCRRC property north of Apple Avenue.

K&R is planning to start tree clearing next week. Tree clearing will be primarily at Crockery Creek; however, some trees within the public right of way will also be removed to allow for force main installation.

Milbocker was off-site this week awaiting arrival of additional force main materials.

Anticipated work activities for the coming week:

  • Milbocker continues force main installation along 64th Avenue.
  • Continue receiving force main materials.

Progress Report:

This week Miller Bridge completed the deck pour, and continued work buttoning up the trail, working on finishing the restoration and starting work on the 128th Avenue section of the trail.

Upcoming Work:

Next week they will work on tearing down the deck forms, and likely start on the parapet walls that will separate the traffic from the new pathway lane.

On the trail they will continue to work on the 128th Avenue section, and pavers will finish paving the gaps in the path early in the week, and anticipate paving the 128th Avenue section by the end of the week.

 

Video of Miller Bridge deck pour:

Progress Report:

Materials for the new lift station have been delayed due to multiple factors outside of Dean’s control. Dean’s now plans to begin work again around the new lift station in early December with hopes of starting up the new lift station by the end of the year.

This Week:

  • Montgomery completed the water service replacements on the north half of Daylor Drive.
  • Concrete sidewalk and driveways were poured on Audley Drive.
  • Topsoil has been spread along Audley Drive and Montgomery plans to hydroseed the disturbed areas on Friday.

Next Week:

  • Concrete crews are scheduled to be on site Monday and will begin driveway and sidewalk replacement on Daylor Drive.
  • HMA road patches will be paved as necessary.
  • Lawn restoration will be completed along Audley Drive.
  • Montgomery will start to wrap up the project for the winter.

Progress Report:

Water main installation at the Ox Creek stream crossing has been completed. Water service installation to property lines has begun on S Euclid between Britain Ave and Highland Ave. All intersections and driveways that were disturbed due to water main construction have been restored.

Upcoming Work:

Pressure testing and disinfection of the water main on S Euclid Ave between Empire Ave and Britain Ave will occur over the next couple of weeks. Water service installation to property lines will also continue over the next week.