K&R completed tree clearing. No additional project work on Contract No. 2 anticipated until spring.
© 2024 Prein&Newhof, All Rights Reserved
K&R completed tree clearing. No additional project work on Contract No. 2 anticipated until spring.
Milbocker remains off-site awaiting arrival of additional force main materials. Milbocker is planning to re-mobilize the week of December 2.
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week:
K&R is planning to start tree clearing next week. Tree clearing will be primarily at Crockery Creek; however, some trees within the public right of way will also be removed to allow for force main installation.
Milbocker was off-site this week awaiting arrival of additional force main materials.
Anticipated work activities for the coming week:
Progress Report:
This week Miller Bridge completed the deck pour, and continued work buttoning up the trail, working on finishing the restoration and starting work on the 128th Avenue section of the trail.
Upcoming Work:
Next week they will work on tearing down the deck forms, and likely start on the parapet walls that will separate the traffic from the new pathway lane.
On the trail they will continue to work on the 128th Avenue section, and pavers will finish paving the gaps in the path early in the week, and anticipate paving the 128th Avenue section by the end of the week.
Video of Miller Bridge deck pour:
Progress Report:
Materials for the new lift station have been delayed due to multiple factors outside of Dean’s control. Dean’s now plans to begin work again around the new lift station in early December with hopes of starting up the new lift station by the end of the year.
This Week:
Next Week:
Progress Report:
Water main installation at the Ox Creek stream crossing has been completed. Water service installation to property lines has begun on S Euclid between Britain Ave and Highland Ave. All intersections and driveways that were disturbed due to water main construction have been restored.
Upcoming Work:
Pressure testing and disinfection of the water main on S Euclid Ave between Empire Ave and Britain Ave will occur over the next couple of weeks. Water service installation to property lines will also continue over the next week.
© 2024 Prein&Newhof, All Rights Reserved