Progress Report:
Riverworks is still continuing efforts constructing the large boardwalk on the corner of Pettis where they are nearly 50% complete with the structural elements of the boardwalk. On the West side of that boardwalk, piles for the smaller boardwalk have been completely installed, but further progress will be slowed until after the larger boardwalk is completed.
Terracon has begun partial removals of driveways along Cannonsburg. Integrity made it on site this week to begin the block wall construction and has made significant progress on the first wall, installing both over 100 feet of base and middle blocks.
Upcoming Work:
Riverworks will continue construction on the larger boardwalk into next week. Terracon will continue removing driveway approaches into next week. Integrity will continue construction on the retaining wall into next week.