FRIDAY, OCTOBER 28, 2022
This Week: Remaining concrete curb and gutter was replaced. Base course paving of Northville Drive was completed. Sidewalk replacement continued along Northville Drive. There is
This Week: Remaining concrete curb and gutter was replaced. Base course paving of Northville Drive was completed. Sidewalk replacement continued along Northville Drive. There is
This Week: Montgomery completed final lawn restoration in the Cottages on the Rogue Neighborhood. Remaining Work: Repair damaged irrigation system at the
This Week: Concrete curb work and concrete driveway work was completed along Algoma Avenue. Lawn restoration along Algoma Avenue continued. Water service installation along Algoma
This Week: The rest of the paving work was completed on the project. Dean’s worked on final project clean up. Lane striping was repainted along
Please use caution while driving through the work zone as the Contractor continues to work on site cleanup. Work completed/in progress from the
Progress Update Approximately 500 feet of sanitary sewer and 1200 feet of water main have been installed to date, as shown on the map above.
Work Completed This Week Placed top course of asphalt on Lakeview St, Lewis St, and Muskegon Ave. Continued landscape restoration on Lakeview St, Lewis St,
This Week: CL Trucking located and repaired a leak in the new 12-inch water main just south of 11 Mile Road. After the leak was
This Week: Montgomery was back on-site Friday to begin final lawn restoration in the Cottages on the Rogue Neighborhood. Next Week: Montgomery will complete final
This Week: Concrete curb and gutter was replaced at side streets along Pine Island Drive. Concrete sidewalk was replaced at Pendleton Drive. Driveway restoration was
© 2023 Prein&Newhof, All Rights Reserved