FRIDAY, OCTOBER 21, 2022
This Week: Some asphalt driveways were paved (base course only) earlier in the week. Sidewalk replacement continued along Northville Drive. Manhole covers and catch basin
This Week: Some asphalt driveways were paved (base course only) earlier in the week. Sidewalk replacement continued along Northville Drive. Manhole covers and catch basin
Current Status/Progress Report Thirty-two (32) houses have connected to the municipal water system (40% of the project area). You may schedule the connection with your
Work completed: Water main was installed to the project limit and pressure tested. Pipe was chlorinated and received a passing sample and is waiting on
This Week: Dean’s completed the 16-inch transmission main construction along Pine Island Drive. Next Week: Concrete curb and gutter will be replaced on Monday
This Week: 12-inch water main along Algoma Avenue was completed. 8-inch water main along Algoma Avenue north of 11 Mile Road was completed. CL Trucking
This Week: Final paving was completed on Green Timbers and in the Cottages on the Rogue neighborhood. Next Week: Montgomery will be back on
This Week: Sanitary sewer lateral replacement was completed. Storm sewer replacement was completed. Sidewalk and concrete driveways were replaced on Northville Drive and Leelanau Drive.
Although we had an extraordinarily wet week, we were able to get some work done out on the construction sites in Whitehall this week.
Work completed/in progress from this past week: Approximately 1,000 feet of watermain has been installed from Territorial Road to 300 feet south of Orchard Drive.
Current Updates Crews have begun work on the restroom and maintenance building. Footings and foundation walls and underground utilities are complete for both. Masonry block
© 2023 Prein&Newhof, All Rights Reserved