June 29, 2026
Progress Report:
Last week, Dykema Excavating continued installing the 24-inch transmission main pipe northbound past Tyler Street on 48th Avenue. The road crew continued grading the road with aggregate base from Port Sheldon Street to just south of Wellington Street near the N. Schut Greenhouses. Residential driveways were also prepared for paving. Testing also continues on the already installed transmission main.
In addition, the Tyler Street water main project (Contractor: DeSal Excavating) began with installation of 12-inch water main crossing 48th Avenue on Tuesday. Water main continued to be installed on Friday to the west along Tyler Street. Paving occurred on a portion of Tyler Street on Wednesday.
Upcoming Work:
Dykema will continue installing transmission main northbound towards Baldwin and will also be working on testing of the transmission main. Paving south of Tyler Street to Port Sheldon Street is expected to take place sometime in mid-July once testing of the transmission main is completed.
DeSal will continue installing 12-inch water main next week and may be complete installation of the water main by the end of next week. Testing would then follow installation.
Notes:
48th Avenue remain closed to through traffic from Port Sheldon Street to Baldwin Street. Through traffic should continue to follow the posted detour signage.
Residents along 48th Avenue should also be aware that Tyler Street is closed from 56th Avenue to 48th Avenue.
Local traffic needing access to Chatsworth Creek Drive and Faringdom Grove Drive should do so by turning onto 48th Avenue from Port Sheldon Street if possible. While the contractor will continue to maintain access to 48th Avenue from either direction, dump trucks are anticipated to be lined up north of Tyler Street throughout next week.
We ask the public to respect the workers and the closed road. Police will continue to monitor the site to ensure safe working conditions and to ensure the road is only being used by those who live or work on this road. Local traffic should continue to be especially mindful as there will be multiple crews on site next week.
