Archives: Construction Updates

FRIDAY, OCTOBER 21, 2022

This Week: Some asphalt driveways were paved (base course only) earlier in the week. Sidewalk replacement continued along Northville Drive. Manhole covers and catch basin

Read More »

FRIDAY, OCTOBER 21, 2022

Current Status/Progress Report Thirty-two (32) houses have connected to the municipal water system (40% of the project area). You may schedule the connection with your

Read More »

FRIDAY, OCTOBER 14, 2022

This Week: Dean’s completed the 16-inch transmission main construction along Pine Island Drive.   Next Week: Concrete curb and gutter will be replaced on Monday

Read More »

FRIDAY, OCTOBER 14, 2022

This Week: Sanitary sewer lateral replacement was completed. Storm sewer replacement was completed. Sidewalk and concrete driveways were replaced on Northville Drive and Leelanau Drive.

Read More »

TUESDAY, OCTOBER 11, 2022

Current Updates Crews have begun work on the restroom and maintenance building. Footings and foundation walls and underground utilities are complete for both.  Masonry block

Read More »