Work began on Schedule and as promised on Wednesday, August 16, 2023.

 

Work Completed this Past Week:

  • Traffic control signs and barricades were installed
  • Asphalt Pavement was removed
  • Concrete curb and gutter was removed
  • Driveways have been removed between the curb and sidewalk
  • Materials and equipment were delivered to the site

 

Work Anticipated Week of August 21, 2023

  • Additional removals will take place including sidewalk
  • Begin installation of water main pipe

 

Work Anticipated Week of August 28, 2023

  • Continued installation of water main pipe
  • Gather information for scheduling water service replacements