Work began on Schedule and as promised on Wednesday, August 16, 2023.
Work Completed this Past Week:
- Traffic control signs and barricades were installed
- Asphalt Pavement was removed
- Concrete curb and gutter was removed
- Driveways have been removed between the curb and sidewalk
- Materials and equipment were delivered to the site
Work Anticipated Week of August 21, 2023
- Additional removals will take place including sidewalk
- Begin installation of water main pipe
Work Anticipated Week of August 28, 2023
- Continued installation of water main pipe
- Gather information for scheduling water service replacements