Underground utility work continued this week on Wood Street with both water main and sanitary sewer installations.  Water main connections to the existing system were completed in Dryden as well as Woodlawn Court.  Underground utility work will continue on Wood Street next week with Sanitary sewer moving west from Hart Street.

Work Completed last Week

Anticipated Work Next Week

Please Note: Underground utility work continues on Wood street.  Dave’s party store is accessible on Hart Street from the north.