Work Completed This Week

  • Road restoration has begun on Poliski Drive and Beidler Street (south of Hackley).
  • New storm sewer has been installed on Poliski Drive and Beidler Street (south of Hackley).
  • Beidler Street (north of Hackley) and Young Avenue have been top soiled and hydroseeded and all castings have been raised to finished grade.

Anticipated Work Next Week

  • Gravel will be installed on Poliski Drive and Beidler Street (south of Hackley) early in the week
  • Concrete curb and gutter installation on Poliski Drive and Beidler Street (south of Hackley) will begin on Wednesday, July 29.
  • Beidler Street between Alberta Avenue and Pulaski Avenue, and Pulaski Avenue from Kinsey Street and Beidler Street is scheduled to be milled on Tuesday, July 28.
  • Sanitary sewer installation will continue on Beidler Street to the south to Pulaksi Avenue.
 

Current Road Closures

  • Beidler Street is closed from Hackley Avenue to Young Avenue.
  • Young Avenue is closed near Beidler Street.
  • Beidler Street (south of Hackley) and Poliski Drive are still under construction and a temporary road is being maintained by the contractor for access to affected businesses and residents.
  • STARTING MONDAY, JULY 27: Beidler Street between Alberta Avenue and Pulaski Avenue, Pulaski Avenue between Henry Street and Beidler Street, and Pulaski Avenue between Kinsey Street and Henry Street will be closed to through traffic.  Henry Street will remain open and not be affected.