Current Road Closures

  • Crowley Street is closed with a posted detour from Young Avenue to Laketon Avenue and will likely be open to traffic later next week.
  • Beidler Street is closed from Hackley Avenue to Young Avenue.
  • Hackley Avenue is scheduled to be closed between Beidler Street and Poliski Drive starting Monday, June 22.  Approximately 3 weeks of closure on Hackley is anticipated at this time.

 

Work Completed This Week

  • All of the concrete curbs, driveways, and sidewalk were installed on Crowley Street between Laketon Avenue and Young Avenue.
  • The base course of asphalt was paved on Thursday on Crowley, all castings have been raised, and top soil has been spread over the disturbed areas.
  • The 12-inch sanitary sewer on Beidler Street has been installed up to the alley between Hancock Avenue and Wilson Avenue.

 

Anticipated Work Next Week

  • Kamminga & Roodvoets, Inc. plans to continue installing the sanitary sewer on Beidler Street between Wilson Avenue and Hackley Avenue.
  • The top course of asphalt is scheduled to be paved on Crowley Street on Wednesday, June 17.
  • Work will begin on the new 6-inch water main loop on Beidler Street and Poliski Drive, south of Hackley Avenue on Monday, June 15.