Work Completed This Week
- Jackson-Merkey Contractors, Inc. continued installing sanitary sewer on Strong Avenue to the west of Jefferson Street and Jefferson Street north of Strong Avenue.
- Ryerson Brothers Construction and Jackson-Merkey installed various water services on Strong Avenue and Jefferson Street.
Anticipated Work Next Week
- The remainder of the water services on Strong Avenue will be installed next week.
- Sanitary sewer installation will continue on Jefferson Street north to Merrill Avenue, and on Strong Avenue between Jefferson Street and Sanford Avenue.
- Storm sewer installation on Jefferson Street may begin near the end of the week.
Current Road Closures
- Mason Avenue from Third Street to Fourth Street.
- Strong Avenue from Fourth Street to Sanford Street.
- Jefferson Street from Campus Street to Monroe Avenue.
- Sanford Street at Strong Avenue.
- Third Street from Mason Avenue to Jefferson Street.