Work Completed this Past Week:

  • Today, the first layer of asphalt is being installed on 7th Street
  • Concrete work was done on ramps, curb and gutter, driveways and sidewalks throughout 7th Street, 6th Street, Summit, Amsterdam and Oakwood

 

Work Anticipated Week of November 13, 2023

  • Manhole covers will be raised to the final pavement elevation
  • Topsoil and restoration of lawn areas will be ongoing
  • Any remaining concrete work will be completed
  • Final course of asphalt will finished by the end of the week

 

Work Anticipated Week of November 20, 2023

  • Punchlist work
  • Topsoil, Grading and seeding
  • Signs, Pavement markings

 

Roads should be re-opened and all traffic control signage removed before Thanksgiving.