Work Completed this Past Week:
- Today, the first layer of asphalt is being installed on 7th Street
- Concrete work was done on ramps, curb and gutter, driveways and sidewalks throughout 7th Street, 6th Street, Summit, Amsterdam and Oakwood
Work Anticipated Week of November 13, 2023
- Manhole covers will be raised to the final pavement elevation
- Topsoil and restoration of lawn areas will be ongoing
- Any remaining concrete work will be completed
- Final course of asphalt will finished by the end of the week
Work Anticipated Week of November 20, 2023
- Punchlist work
- Topsoil, Grading and seeding
- Signs, Pavement markings
Roads should be re-opened and all traffic control signage removed before Thanksgiving.