Work Completed this Past Week and Recently:

  • Road restoration preparation on Wilson and Petrie west of Grand Haven Road – Road base gravel has been spread
  • Preparations are being made to mill the remaining asphalt and then pave the entire roadway
  • Private water service connections

 

Work Anticipated Week of November 6, 2023

  • Tentative schedule for 1st course of asphalt on Wilson and Petrie is scheduled for Monday, November 6 – Weather Dependent
  • Milling the remaining asphalt on Wilson and Petrie
  • Concrete restoration work on driveways on Wilson and Petrie
  • Asphalt driveways on Petrie and Wilson
  • Top course of asphalt on Petrie and Wilson late in the week (Nov 9 or 10 – again weather dependent)
  • Road restoration on Wilson and Petrie including grading and placement of gravel road base material
  • Additional private side water service installations

 

Work Anticipated Week of November 13, 2023

  • Lawn restoration and mailboxes on Petrie and Wilson
  • Punchlist work
  • Continue to connect private side water services through the winter

 

Construction is scheduled to be completed in November 2023.  Please watch for more information about connecting to the new water main for those residents connecting to the new water main.