Work Completed this Past Week:

  • Concrete driveways were poured
  • Concrete sidewalks were poured
  • Concrete curb and gutter was installed
  • PLEASE NOTE: Some of this concrete work was damaged with the snow and it will need to be replaced.
  • Gravel road base is being touched up and graded and readied for asphalt.
  • An additional hydrant was replaced at 6th Street and Oakwood

 

Work Anticipated Week of November 6, 2023

  • The first course of asphalt is tentatively scheduled for Monday, November 6, 2023
  • Manholes, valves and other structures will be adjusted to the final elevation after the first layer of asphalt is installed
  • Finish any remaining concrete work on sidewalks, ramps, repair any damaged concrete
  • Backfilling and restoration will continue

 

Work Anticipated Week of November 13, 2023

  • Final course of asphalt
  • Punchlist work
  • Topsoil, Grading and seeding
  • Signs, Pavement markings

 

Roads will be reopened in mid-November 2023 and the project will be completed!