The reconstruction of Peck Street has begun at full force on Phase 1 (Southern to Merrill)!

 

Work Completed This Week

  • Forest Ave. to North end project limits were saw cut.
  • Various trees within the right-of-way have been removed.
  • Asphalt Pavement was milled from Forest Ave. to North end project limits.
  • Concrete pavement between Strong Ave. and North end project limits was removed.
  • Well points placed for dewatering were installed at Strong Ave & Peck St.
  • Began placing sanitary sewer main line from Strong Ave. towards the North.

 

Anticipated Work Next Week

The primary Contractor anticipates:

  • Continuing to remove concrete pavement.
  • Continue placing main line sanitary sewer and laterals.