This Week:

  • Montgomery completed water service installation on Northgate.
  • Montgomery completed water main tie-ins at Daylor and the north end of Northgate.
Next Week:
  • Montgomery will complete the last water main tie-in at the south end of Northgate. This is tentatively scheduled for Monday.
  • Montgomery will begin project cleanup.
  • Concrete sidewalk will begin to be replaced.