Significant progress has been made on the project over the last two weeks. Water main installation on Mill Pond Trail is nearly complete and testing will begin shortly!
Work Completed since last update.
- All the water main has been installed on Mill Pond Trail. The main was installed a few sections to facilitate testing and cleaning and the sections will be connected later once testing is complete.
- Water services along Silver Creek continue to be installed, final connections at most homes have not been completed yet but the bulk of the piping is installed.
Anticipated Work for the Coming Week
- The water main will be installed across Silver Creek at Mill Pond Trail. This will require a full road closure of Silver Creek at Mill Pond Trail starting at 8:30 Monday April 21 and continuing through Tuesday April 22.
- Following installation Silver Creek Crossing the testing of the new main will begin this work and will take approximately a week to complete.
- Water service installation will continue along Silver Creek, this work will be scheduled with each property owner.
Please be aware of the construction work, do not assume that equipment operators can see you. Do not approach heavy equipment.