Progress Report: New water main on Martin and Lulu has been installed and restoration is underway. New water main connections along West Main are underway and should be completed next week.
Upcoming Work: Once the connections at West Main are completed, water main work will start along Pinehurst from West Main to Hillsdale. Once the water main is installed, it will be tested and then individual water service replacements will begin. Residents will be contacted by phone (SWT Excavating is the contractor) if in-home work is required. If only outside work on the service is needed, a door hangar notification will be posted. All residents will receive a new copper water service line in the road right-of-way. Water services outside of the right-of-way and into the homes will be replaced with copper if the current service is galvanized steel or lead.