Approximately 500 feet of sanitary sewer has been installed on Pipestone Road and Carlton Ave. All sanitary sewer installation in Phase 1 of the project has been completed.

 

Up Next

Restoration of Pipestone Road and Carlton Ave pavements is planned for next week. After Pipestone and Carlton are reopened to traffic, the project can move into Stage 2, which includes closing M-139 for a sewer crossing. M-139 traffic will follow a detour along Pipestone Road and Napier Avenue.  The portion of M-139 between Napier and Pipestone will remain open to local businesses and side streets. The M-139 closure is anticipated to begin during the week of August 21, will remain closed through the following week, and be completed with reopening to traffic before labor day weekend.