Construction on the S. Euclid and Britain Ave Water Main project has begun! Approximately 1500 linear feet of 16-inch water main has already been installed on S. Euclid Ave from Empire Ave to the north, with the exception of the stream crossing at Ox Creek. The connection of the new S. Euclid water main to the existing Empire Ave water main has also occurred.
Upcoming Work: Construction of 16-inch water main towards Britain Ave will continue through the end of next week. The stream crossing at Ox Creek has yet to be scheduled.© 2024 Prein&Newhof, All Rights Reserved