Gravity Sewer Construction

Progress Update: All of the sanitary sewer installation on the project has been completed! The highway crossing portion of the project will be done in a future year in coordination with MDOT.

Up Next: Remaining punchlist items, including paving of the hotel access drive and Super 8 parking lot, are scheduled to occur over the next couple of weeks.