Last week was focused on concrete installation.  This week will include more concrete improvements and topsoil restoration. 

Work Completed Last Week

  • Installed concrete curb and gutter throughout the project with the exception of the radii at Imperial Drive and Thornwyk Drive.  Sidewalk and driveway approaches were installed on the west side Kinney on the north end of the project.
  • The storm sewer was partially televised using a CCTV camera to verify proper installation.
  • The remaining storm sewer was removed within the project.

Anticipated Work This Week

  • Concrete improvements will begin continue between Edinboro Street and Leonard Avenue.  For all affected residents, please refrain from driving over the concrete sidewalk until driveways are reopened (approximately 7 days to allow for proper curing).  Please park on the gravel surface of the new road or a nearby side street.
  • The grassy areas north of Edinboro Street will continue to be restored and graded with topsoil.
  • Asphalt paving has not been scheduled yet but the first course of asphalt is planned to be installed over the next 1 to 2 weeks.