Private water service installation continued throughout the project area. As of December 23, thirty-seven (37) houses – 65% of the 2021 project area – have connected to the municipal water system. See status map above for reference.

Homeowners must schedule the work directly with the contractor they selected. Please contact Jeremy Kamp (contact info to the left) if you have any questions.

April 2022

What to Expect

January 2022 – Spring 2022
Spring of 2022