Current Status/Progress Report

As of December 23, fifty-five (55) houses – 77% of the project area – have connected to the municipal water system. See status map above for reference.

All water services are available for connection. Homeowners must schedule the work directly with the contractor they selected. Please contact Jeremy Kamp (contact info to the left) if you have any questions.

 

What to Expect

December – Spring 2022
  • Private water service installation
  • Asphalt repairs on Meek Drive and Korben Woods Court in the Spring of 2022