Work to Date
- Watermain has been placed along Burger between Goodwood and Tanglewood.
- The main has passed all testing and has been tied into the existing system.
- Crews have completed stubbing water services out to the right-of-way line.
- Watermain has been placed along Tripoli between Burger and Tuscany and on Tripoli Court.
- The main has passed all testing and has been tied into the existing system.
- Crews have completed stubbing water services out to the right of way line.
- Watermain has been placed along Cimarron between Goodwood and Tuscany.
- The main has passed all testing and has been tied into the existing system.
- Crews have completed stubbing water services out to the right of way line.
- Watermain has been placed along Burger between Tanglewood and the west end of the job limits (6950 Burger).
- The main has passed all testing and has been tied into the existing system.
- Crews have completed stubbing water services out to the right of way line.
- Watermain has been placed along Tuscany between Burger and the west end of the job limits.
- The main has passed all testing and has been tied into the existing system.
- Crews have completed stubbing water services out to the right of way line.
- Contractor has completed the installation of the new storm sewer on Burger between Tanglewood and the bayou and between Tuscany and 6920 Burger.
- Watermain has been placed along Tanglewood between Burger and Thornapple River Drive.
- Pressure testing and chlorination of the new main is underway.
- Restorative efforts are continuing, and damaged irrigation systems are being repaired.
Work Upcoming
- Watermain installation on Tricklewood is expected to begin on Thursday July 13, starting at the Tanglewood intersection moving north towards Brookhills.
- Beginning Monday July 17th, there will be traffic shifts on Thornapple River Drive between Thornhills and Ridgemont so crews can cross Thornapple River Drive with watermain at Tanglewood and Brookhills. This work is expected to last two weeks and two-way traffic will be maintained.
- Crews will continue restorative efforts in completed areas.
General Notes
- Residents should be aware that after your yard has been dug it may be up to a month before we are able to complete the work and repair irrigation systems.
- The contractor will be responsible for establishing grass growth. For best results residents are encouraged to regularly water the hydroseed and mow down any weeds that do come in.