Work Completed This Week:
- Completion of Water Main testing for new length installed between Lincoln and Lebouef. New length is tied-in to system at Lebouef.
- Continuation of Storm Sewer installation from Lincoln to Muerer Court.
- Install new water services west of Lebouef
- Finalize storm sewer installations
- Grading of roadway east of Lebouef