Work continues to progress on Courtland St and Northland Dr. Other than a few sections of sidewalk, the concrete improvements have been completed and are ready for use. The base course of asphalt has been paved in the sewer reconstruction area. Preparations have been made for the paving of the top course of asphalt. Top soil, mulch and hydro seed have been installed throughout the project for lawn restoration.

Up Next

The top (and final) course of asphalt will be paved throughout the entire project on Thursday. Traffic may be partially restricted when this work is being performed. Pavement markings will be installed Friday and Saturday. After this Saturday only incidental construction items remain. The road will continue to be closed and traffic control devices will remain until inspections are complete, however, houses and businesses should be easily accessible after this week.

What you need to know

Please continue to water your lawn. This grass seed, just like any other seed, needs water to grow well.