This was a very hot, yet productive week on the project. Utilities are complete within the block of Loomis from Rath Avenue to James Street and road reconstruction will begin next week.
Work Completed This Week (June 29–July 3)
- Hallack Contracting completed installation of the sanitary sewer, water main and storm sewer from Rath Avenue to James Street.
Anticipated Work Next Week
- Installation of Curb and Gutter from Rath Avenue to James Street.
- Installation of sidewalk and drive approaches from Rath Avenue to James Street.
- Beginning of preparation for paving.