Progress Report

The Contractor, Anlaan Coporation, out of Grand Haven, has been off-site this week due to an emergency project helping the community of Midland, MI.

 

What to Expect Next Week

Anlaan will be off-site again next week as they finish up their work, but they plan to be back to work on the Spoonville Trail on Monday, July 13. At this point, work will resume with grading the path along Leonard Street from 120th Avenue to the Terra Verde Golf Course entrance, placing concrete sidewalk at the trailhead parking lot on 120th Avenue, and beginning to set the foundation piles for the boardwalk sections.